Constructed a sheet pile retaining wall along the north face of the existing Platte River Lower Weir to prevent further undermining. Filled annular space between the sheet piling and weir concrete pile cap with peastone. Installed riprap along the south face of the weir to fill undermined areas and protect from further erosion.

Platte River Lower Weir Repair

Bluebird Demolition

Removal of existing restaurant structure near the Leland River to make way for renovation, opening Spring 2024.

Discovery Pier Phase 1

  • Dredged 22,000 yds - hauled offsite

  • Installed round piles for docking system

  • Installed permanent sheeting with Waller Tie Back system

  • Installation of flotation dock system

Discovery Pier Phase 2

  • Repurposed an old coal dock into a public park

  • Hauled contaminated fill offsite

  • Site utilities (water, sewer, electric)

  • Site grading

  • Site concrete

  • Asphalt paving

Antrim County Bayshore Project

  • Existing removals

  • 400 LF of permanent sheeting

  • 3200 tons of rock revetment

TCAPS Montessori

  • Reclaimed wetland areas

  • Removed 150,000 CYD of muck

  • Imported and placed with density 32,000 CYD of sand

  • Foundation Prep

  • Site Utilities

  • Site Concrete

  • Asphalt Paving

TCAPS Athletic Fields

  • Existing site removals

  • 70,000 CYD of earthwork

  • Underground utilities

  • Site shaping using GPS

  • Site concrete

  • Asphalt paving